Brochure
Bristol
Significant assets
• Proof pressure bay for SCMs
• 2 Fixed stands for flushing and 4 for SCM testing
• 5 Environmental stress screening (ESS) chambers
• Hyperbaric chamber (270-bar)
• P-SPICE and Hypac design stations for analysis
• Clean room (Assembly SCMs, DCVs, HPIs)
Aztec West
This recently expanded facility is our Center of Excellence for Engineering, Procurement &
Construction – a major hub for all our subsea installation and intervention activities around the
world. The local team includes some of our most experienced project managers, application
engineers and logistics experts, and is involved at all stages of the subsea field lifecycle – from
FEED studies and system design, to installation, service, expansion and intervention.
Footprint
Area
m
2
(ft
2
)
Subsea Systems 2,444 (26,307)
GE Capital 1,846 (19,875)
Nailsea
Established over 35 years ago, our Nailsea facility continues providing leading-edge
design, manufacturing and testing of subsea production control systems – including
concept definition and FEED studies. This is the primary location for project management,
engineering, procurement, and R&D activities for our Subsea Controls projects worldwide.
The team also designs smart applications for remote monitoring, diagnostics and flow
integrity control of subsea facilities.
Footprint
Area
m
2
(ft
2
)
Total Site 5 acres
Offices 13,000 (139,900)
Workshops 13,500 (145,300)
Yard 16,398 (176,500)
Assembly & Integration 2,896 (31,170)
& Test (AIT)
SIT Area 2,896 (31,170)
Electrical Assembly 1,646 (17,720)
MCS Assembly 76 (818)
ESS 549 (5,909)