Fact Sheet
You retain your existing cubicle, overhead bus-work, and cabinet
doors. We replace the diode rectifier, refurbish the on-line repair
switch, replace the manifolds with stainless piping and valves,
On-Site Factory Installation
Electrical Scope Field Service Level 1 Level 2
Remove existing diode banks X X X
Remove existing wiring X X X
Remove existing annunciation devices X X X
Clean/inspect 5-Pole switch X
Refurbish 5-Pole Switch (resilver contacts) X X
Install new diode bridges X X X
Install new bridge wiring harnesses X X X
Install new interface module X X X
Install new annunciator panel X X X
Electrical validation testing X X X
Mechanical Scope Field Service Level 1 Level 2
Remove all existing copper tubing X X X
Remove existing isolation valves X X X
Install new stainless steel isolation valves X X X
Install new stainless stator water connection manifold X X X
Route new cooling water hoses (stainless clad) X X X
Flow and pressure testing X X X
Stator water flow calibration X X X
Cabinet Scope
Field Service Level 1 Level 2
Install new Lamicoid lables
X X X
Strip, prep and powder coat cabinets (interior and exterior)
X
Inspect/repair door gaskets
X
Inspect/repair door handles and locking mechanism X
Replace door-mounted filter racks and filters
X
and provide a new, more reliable diagnostic indicator panel.
GE is helping you reset the clock on the Alterrex diode system.