Step 6 Energize Power Plant
Start up
Remove all converter modules from the power plant if
previously installed
Insert a single converter and turn on the input breaker
to this converter. This will apply input voltage to the
controller and system load bus.
The controllers’ self-diagnostic will start within 30
seconds after power has been applied to the load bus
Normal operation is indicated by the Green illuminated
front display
Pulsar Edge Controller
Normal Operation
Step 7 Install Converter Modules
Module Installation
Insert converter modules
Converters can be added or removed with the
power plant energized
Status LEDs:
Normal = Green
Input Fail = Amber
Fail = Red
Green during
normal
operation