WALL PLENUM
Since the unit itself does not install in the wall opening, 
the use of a plenum is necessary to contain and separate 
the outdoor air paths. The plenum must be able to hold 
water in the bottom without 
leaking into the wall cavity. It also 
must have a “splitter" to separate 
the outdoor air paths and prevent 
the discharge air from being drawn 
back into the unit.
The wall plenum is the first 
component to be installed. 
GE Appliances model RAVWPT15 
is available for use with wall 
thicknesses of 8" to 15". 
The plenum is to be installed square and level in the 
opening and secured to the wall construction with screws 
or nails in the sides located a minimum of 2" up from the 
bottom of the plenum. No nails or screws may be used 
in the bottom or top of the plenum to prevent water 
entering the wall cavity.
The plenum is not load bearing, so a proper header needs 
to be installed above the plenum the same as over any 
window opening in the wall. If the building construction 
is brick, concrete block or other non-self-supporting 
material, a lintel must be installed over the plenum 
opening. The plenum must be caulked to the wall, both 
to the outdoor wall face and to the interior wall, along 
all four sides to prevent air and water infiltration. 
WALL PLENUM MODELS:
RAVWPT15-For installations with walls 8" to 15" thick. 
REPLACEMENT OF OLDER GE VERTICAL 
PRODUCT 
When replacing a previous model GE Appliances vertical 
unit with a new AZ95 series vertical air conditioner, one 
of three transition plenums must be used. 
Differences in chassis designs between the prior models 
and AZ95 series require careful installation and planning. 
Changes in drain exit locations, drain routing, electrical 
connections, platform height, conditioned air duct 
location and additional space requirements for installation 
of a transition kit are all items that need to be considered 
when replacing a prior model with an AZ95 series unit. 
The selection of the appropriate transition kit is based on 
the original wall plenum being used. If a RAVTRANS kit 
is already being used to transition an original wall plenum 
to an AZ90/91 series, it will need to be removed and a 
RAVTRANS2 kit will need to be installed prior to installing 
an AZ95 series unit. Please reference the following chart 
to determine which transition kit is needed. Before 
starting the conversion, be sure there is adequate closet 
space to meet the manufacturer's recommend minimum 
clearance requirements. 
INSTA-PLATFORM
™
The AZ95 series requires the use of a separate drain 
platform accessory (RAVDPLAT). This accessory supports 
the chassis and positions it properly to seal to the wall 
plenum. Also, it serves as the drain pan for the chassis 
with connections for both a primary and secondary 
drain. This innovative accessory saves time and money 
by eliminating the need for field-fabricated support 
platforms. It also greatly simplifies chassis removal 
from the closet because the plumbing connections are 
made to the platform as opposed to the chassis itself. 
The drain platform height is determined based on the 
position of the RAVWPT15 wall plenum. The bottom edge 
of the drain platform is flush with the bottom edge of the 
wall plenum. Technically, the bottom edge could be set 
to floor level, but that would likely make connecting to 
a building drain system difficult. In most installations, it 
will be desired to raise the platform several inches off the 
floor. This can easily be done using 2"x4" lumber cut to 
length and positioned in the integrated support pockets 
of the RAVDPLAT. Only two support legs are needed as 
the exterior side is supported by the wall plenum.
The primary drain can be directed out either side or the 
front of the drain platform through sidewall notches in 
the platform. If the platform is elevated for drainpipe 
clearance below, the primary drain can run any direction 
desired. The secondary drain is to be piped through the 
wall plenum to the exterior of the building. 
For further detail, please see the RAVDPLAT Installation 
Instructions. 
COMPONENTS & INSTALLATION
Each Zoneline single packaged vertical unit requires a 
drain platform, wall plenum, exterior grille, unit, remote 
thermostat, power connection kit, return air grille/access 
panel, filter, ductwork and supply registers. 
The drain platform legs, ductwork and supply registers 
are field supplied. Each of the other components is 
ordered separately. The drain platform, wall plenum and 
exterior grille are specifically designed to interface with 
the GE Appliances Zoneline Vertical chassis and must be 
purchased from the same source as the unit. Custom 
exterior grilles may be used but must comply with the 
requirements shown on page 10.
The remote thermostat and the return air grille are 
offered as accessories by GE Appliances, but may be 
purchased from a source other than GE Appliances. 
If a non–GE Appliances thermostat is being used, 
it should meet the general thermostat requirements 
mentioned on page 12. Any custom return air grille 
being used should offer a louvered area as large as 
the GE Appliances offering or larger. 
Transition Kit 
Model
AZ75/85 Series (used a beige color plenum)
AZ90/91 Series RAVWPT8 plenum ONLY 
(black, 5.5"-8" deep)
AZ90/91 Series RAVWPT14 plenum ONLY 
(black, 8"-14" deep)
1.5"
N/A
N/A
RAVTRANS2
RAVTRANS3
RAVTRANS4
Transition From
Additional Closet
Clearance For Kit
NOTE: For AZ90/91 model replacement, make sure no 
existing RAVTRANS kit is being used. If so, discard and use 
RAVTRANS2
Preliminary specifications. Subject to change.