Installation Guide

ASTM E2112-01* and AAMA 2400-02* recom-
mend the use of a minimum 9 inch wide flashing
membrane beyond the rough opening.
Grace recommends a 12 inch wide flashing mem-
brane for proper waterproofing of the window
sill, providing a drainage plane in the rough open-
ing.
Remove any weather-resistive barrier from sill
area prior to membrane installation for full adhe-
sion of the membrane to the structural sill.
Refer to “Table I – Flashing Lengths and Cut
Formulas,” (page 8), to determine appropriate
flashing lengths.
• After the membrane has been installed, roll firmly into place.
Install membrane such that all laps shed water (following the
shingle principle). Always work from the low point to the high
point.
Mechanically fasten the membrane at vertical terminations, as
necessary.
Weather-resistive barrier refers to housewrap, building paper/
felt, Perm-A-Barrier
®
, etc.
Windows/siding should be installed according to the standards
set by the window/siding manufacturers and/or respective
organizations.
Apply Grace Vycor Self-Adhered Flashings only in fair weather
when the air, surface and membrane temperatures are at a
minimum of -4°C (25°F). For temperatures below 5°C (40°F),
keep material warm until use. (Refer to Technical Letter 3.)
Install directly onto a clean, dry and frost-free surface.
Remove dust, dirt and debris. Surfaces shall be smooth and
continuous without voids, damaged or unsupported areas.
Priming is generally not required for most substrates pro-
vided they are clean and dry. However, on concrete,
masonry and DensGlass Gold
®
, apply Perm-A-Barrier WB
Primer at a coverage rate of 6-8 m
2
/L (250-350 ft
2
/gal).
If adhesion is found to be marginal, also prime wood
composition and gypsum sheathing with Perm-A-Barrier
WB Primer at the same coverage rate.
*
Standard Practice for Installations of Exterior Windows,
Doors and Skylights.
**
Standard Practice for Installations of Windows with a
Mounting Flange in Stud Frame Construction.
How to Apply Grace Vycor Self-Adhered Flashing Tapes
PRE-INSTALLATION NOTES
Flashing Location Flashing Lengths and Cut Formulas
Sill Flashing Rough opening width + (2 x flashing width)
Jamb Flashing Rough opening height + (2 x flashing width) – 1 inch
Head Flashing Rough opening width + (2 x flashing width) + 2 inch
Example for 9 inch wide flashing
If rough opening width = 30 inches
If rough opening height = 50 inches
For Sill: 30 inches + (2 x 9 inches) = 48 inches
For Jamb: 50 inches + (2 x 9 inches) – 1 inch = 67 inches
For Head: 30 inches + (2 x 9 inches) + 2 inches = 50 inches
This table will assist in determining the pre-cut flashing
lengths required to properly install window flashing
(as per ASTM E2112-01).
TABLE I – Flashing Lengths
and Cut Formulas
8
7
Refer to our web sites for further product information.