Reflex 105 Balanced Flue Installation Instructions

28
INSTALLATION INSTRUCTIONS
COMMISSIONING
Complete the Commissioning Checklist at the front of this manual
covering:
— Thermocouple soundness checks.
This is to include ensuring the thermocouple is secure on
the pilot bracket assembly, lead connection and integrity.
— Flue checks
— Gas checks
— Log layout - ame picture
For working pressure test, refer to Technical Specications.
Ensure all safety checks listed in the Commissioning Section are
completed, paying particular attention to the glass panel checks
and securing of the glass frame.
Upon completion of the commissioning and testing of the
installation and correct operation of the appliance, the installer must
instruct the user how to operate the appliance.
Guide the user through the User Instructions paying particular
attention to:
a) Regular servicing.
b) Ventilation - point out
the ventilation positions where applicable.
c) Hot surfaces.
d) How the appliance works with the remote control handset
and the modes of operation.
e) How to change settings in the auto mode and program
modes of operation.
f) What to do if the appliance fails to operate.
REPROGRAMMING HANDSET/
CONTROL BOX
To access the control box see Servicing Instructions, - Removing
the Log Burners and Main Control Assembly.
Press and hold the reset button on the control box until you hear
two signals. After the second longer signal:
Release the reset button and within 20 seconds:
Press the DOWN button on the handset until you hear two
additional short signals conrming the new code is set. If there is
a single long signal the code learning sequence has failed or the
wiring is incorrect.
Note: When pressing the DOWN button on the handset if two
beeps are not heard:
Release the DOWN button and CONN will be displayed on the
handset screen. An 8 second count will start on the handset screen
followed by two short beeps conrming the new code is set. If there
is a single long signal the code learning sequence has failed or the
wiring is incorrect.