Conventional Flue
27
1. Commissioning
1.1 Close all doors and windows in the room.
1.2 Ignite the appliance and operate on maximum for 10
minutes.
1.3 Position a lighted smoke match just inside the draught
diverter opening at the rear of the appliance.
1.4 Check all smoke is drawn into the opening, see Diagram 1.
1
Rear of Appliance
Draft diverter lip
Smoke match
1.5 If there is any doubt, run the appliance for a further 10
minutes, and repeat the test.
1.6 If there are any extractor fans in adjacent rooms, the test
must be repeated with the fans running on maximum and
interconnecting doors open.
IF SPILLAGE PERSISTS, DISCONNECT THE APPLIANCE AND
SEEK EXPERT ADVICE.
1.7 Complete the Commissioning Checklist at the front of this
manual covering:
— Thermocouple soundness checks.
This is to include ensuring the thermocouple is secure on
the pilot bracket assembly, lead connection and integrity.
— Flue checks
— Gas checks
— Log layout - ame picture
1.8 Upon completion of the commissioning and testing of the
installation and correct operation of the appliance, the
installer must instruct the user how to operate the appliance.
1.9 Guide the user through the User Instructions paying
particular attention to:
a) Regular servicing (Section 9 of the User Instructions).
b) Ventilation (Section 10 of the User Instructions) - point out
the ventilation positions where applicable.
c) Hot surfaces (Section 12 of the User Instructions).
Commissioning