Instruction Manual

G1000 / GFC 700 System Maintenance Manual - 200/B200 Series King Air Page 7-13
190-00915-01 Revision 8
6. After each configuration setting change, press the ENT key to configure the transponders.
7. Press the ENT key on PFD1 to acknowledge prompt.
8. After completing transponder configuration, deactivate the cursor.
7.5.2 GTX 33( ) Test
Operation of the GTX 33 or GTX 33D Mode-S transponder is accomplished using PFD 1, PFD 2 or the
MFD. Refer to G1000 in King Air 200/B200 Cockpit Reference Guide
, listed in Table 1-2, for basic
operation.
The integrated transponder/altitude reporting system must be verified in accordance with Title 14 of the
Code of Federal Regulations (14 CFR) ยงยง 91.411 and 91.413, every 24 calendar months, or any time
the transponder is removed. This test requires the use of a Mode S ramp generator. Specific instructions
for operating the ramp tester are contained in the applicable operator's manual. Refer to 14 CFR Part 43
Appendices E and F for testing criteria.
Note that for GTX 33D units, the aircraft must be put on jacks to simulate an in-air condition in order to
test the Mode S diversity transmission channel isolation.
If no other service is to be performed, continue to the return-to-service checks in Section 8.
7.6 GDC 74B/GDC 7400 Air Data Computer
Original GDC unit is Reinstalled
No software or configuration loading is required if the removed GDC 74B/GDC 7400 is re-installed.
This does not include units that were returned for repair as their software and configuration files are
deleted during the repair testing process. Continue to GDC 74B/GDC 7400 Test (Section 7.6.1).
Original GDC unit Installed in Opposite Locations for Troubleshooting
No software loading is required if the original GDC #1 and GDC #2 are installed in opposite locations.
Continue to GDC 74B/GDC 7400 Test (Section 7.6.1).
New, Repaired or Exchange GDC unit is Installed
If a new, repaired or exchange GDC unit is installed, the correct software and configuration files must be
loaded to the unit. See Section 3.9, and then continue to GDC 74B/GDC 7400 Test (Section 7.6.1).
New GDC 74B Configuration Module is Installed
The correct configuration files must be loaded if the GDC 74B configuration module has been replaced.
See Section 3.9, and then continue to GDC 74B/GDC 7400 Test (Section 7.6.1).