Instructions / Assembly
6"
(152 mm)
6"
(152 mm)
Center valley metal, overlap metal
horizontal laps a minimum 12" (305mm)
and seal by embedding them in asphalt
plastic cement.
Center full width roll of GAF leak barrier.
Do not place fasteners within 6" (152mm)
of center line. Horizontal laps 6" (152mm) min.
Centre un rollo de ancho completo
de barrera de filtraciones de GAF. No coloque sujetadores
dentro de las 6" (152mm) de la línea central.
Traslapes horizontales a 6" (152mm) como mín.
Carry GAF underlayment at
least 6" (152mm) over
GAF leak barrier.
Lleve la capa base de GAF por
lo menos 6"(152mm) sobre
barrera de filtración de GAF.
Overlap shingles at least 4" (102mm).
over 20" (508mm) wide valley metal.
Embed the shingle ends in asphalt
plastic cement to seal the shingles to
the metal and keep water from
running under them.
Superponga las tejas a por lo menos
4" (102 mm), con más de 20" (508 mm)
de ancho del metal del valle.
Unte los extremos de las tejas en cemento
plástico asfáltico para sellar las tejas al metal
y evitar que el agua corra debajo de ellas.
Centre el metal del valle traslape el metal
en los solapes horizontales un mínimo
de 12" (305mm) y selle untándolos en
cemento del plástico del asfalto.
Recorte las esquinas superiores
de las tejas a 45°para mantener
el flujo de agua hacia el centro
del valle.
Clip the top corners of
shingles 45° to keep water
flow toward the valley center.
Shingles should be separated 6" (152mm) at top of valley. Separation must increase 1/8" (3mm)
per foot towards eaves to handle increasing water volume. Snap chalk lines to ensure
shingles diverge properly in valley.
Parte superior del valle 6" (152mm) de ancho entre tejas.Las tejas deben ampliar 1/8" (3mm)
por pie hacia alero para manejar aumentando volumen de agua. Trace líneas de tiza para
garantizar que las tejas tengan la adecuada divergencia en el valle.
9.
VALLEY CONSTRUCTION – OPEN
Use minimum 20" (508mm) wide aluminum, galvanized steel, copper, or other non-corroding, non-staining metals (24 gauge minimum). Long valleys or local
building codes may require wider metal. Nail the metal on the edges so the nail heads hold it in place. Do not puncture the metal. Nailing through the metal
may cause leaking and buckling due to movement.
CONSTRUCCIÓN DEL VALLE – DE CORTE ABIERTO
Use un ancho mínimo de 20" (508mm) de aluminio, a cero galvaniza do, cobre y otro metal inoxidable que no manche (calibre 24 como mínimo). Los valles
largos o los códigos locales de construcción pueden requerir un metal más ancho. Clave el metal en los bordes de modo tal que las cabezas de los clavos
sostengan el metal en su lugar. No perfore el metal. Clavar a través del metal puede causar filtraciones y ampollamiento debidos al movimiento.