Design Technical Manual
Table Of Contents
- CHAPTER00
- CHAPTER01_General_information
- CHAPTER02_Model_selection
- 1. MODEL SELECTION PROCEDURE
- 2. MODEL LINE UP
- 3. MODEL SELECTION AND CAPACITY CALCULATION
- 4. CAPACITY TABLE COOLING (OUTDOOR UNIT)
- 5. CAPACITY TABLE HEATING (OUTDOOR UNIT)
- 6. CAPACITY COMPENSATION COEFFICIENT
- 7. CAPACITY TABLE COOLING (INDOOR UNIT)
- 7-1. COMPACT CASSETTE TYPE
- 7-2. CIRCULAR FLOW CASSETTE TYPE
- 7-3. CASSETTE TYPE
- 7-4. MINI DUCT TYPE
- 7-5. SLIM DUCT / SLIM CONCEALED FLOOR TYPE
- 7-6. MEDIUM STATIC PRESSURE DUCT TYPE
- 7-7. HIGH STATIC PRESSURE DUCT TYPE
- 7-8. VERTICAL AIR HANDLER TYPE
- 7-9. COMPACT FLOOR TYPE
- 7-10. FLOOR / CEILING TYPE
- 7-11. CEILING TYPE
- 7-12. WALL MOUNTED TYPE
- 8. CAPACITY TABLE HEATING (INDOOR UNIT)
- 8-1. COMPACT CASSETTE TYPE
- 8-2. CIRCULAR FLOW CASSETTE TYPE
- 8-3. CASSETTE TYPE
- 8-4. MINI DUCT TYPE
- 8-5. SLIM DUCT / SLIM CONCEALED FLOOR TYPE
- 8-6. MEDIUM STATIC PRESSURE DUCT TYPE
- 8-7. HIGH STATIC PRESSURE DUCT TYPE
- 8-8. VERTICAL AIR HANDLER TYPE
- 8-9. COMPACT FLOOR TYPE
- 8-10. FLOOR / CEILING TYPE
- 8-11. CEILING TYPE
- 8-12. WALL MOUNTED TYPE
- CHAPTER03_Outdoor_units
- CHAPTER04_Indoor_units
- CHAPTER05_Control_system
- 1. CONTROL SYSTEM
- 2. CONTROL UNITS
- 2-1. SYSTEM CONTROLLER
- 2-2. SYSTEM CONTROLLER LITE
- 2-3. TOUCH PANEL CONTROLLER
- 2-4. CENTRAL REMOTE CONTROLLER
- 2-5. WIRED REMOTE CONTROLLER (Touch panel)
- 2-6. WIRED REMOTE CONTROLLER
- 2-7. SIMPLE REMOTE CONTROLLER (With Operation mode)
- 2-8. SIMPLE REMOTE CONTROLLER (Without Operation mode)
- 2-9. WIRELESS REMOTE CONTROLLER
- 2-10. IR RECEIVER UNIT (for ALL DUCT TYPE)
- 2-11. IR RECEIVER UNIT (for CASSETTE TYPE)
- 2-12. IR RECEIVER UNIT (for CIRCULAR FLOW CASSETTE TYPE)
- 2-13. HUMAN SENSOR KIT (for CIRCULAR FLOW CASSETTE TYPE)
- 2-14. REMOTE SENSOR UNIT
- 2-15. PRESSURE SENSOR KIT
- 2-16. GROUP CONTROL METHOD
- 2-17. COMPARISON TABLE OF CONTROLLERS
- 3. ADAPTOR / CONVERTOR UNITS
- 4. SERVICE & WEB MONITORING TOOL
- CHAPTER06_System_design
- CHAPTER07_Function_setting
- CHAPTER08_External_input_and_output
- CHAPTER09_Notes
- CHAPTER10_Optional_parts
- CHAPTER99
WORK FLOW (EXAMPLE)
Prepare Project Schedule
Refrigerant check
Refrigerant piping work
Drain piping work
Duct work
Insulation work
Electric wiring work
Outdoor unit foundation work
Outdoor unit installation
Address setting
Leak pressure test
Vacuum evacuation and drying
Additional Refrigerant Charge
Gas leakage check
Outside panel installation
Test run and adjustment
Hand over
Customer Training
Refrigerant piping connection (Outdoor unit)
Remote controller installation
Indoor unit installation
Operation chart preparation
● Always check the refrigerant to be used.
● Always use the specified refrigerant.
● Prepare materials / tools matched to the refrigerant.
● Do not purge system with refrigerant.
● Use a vacuum pump with check valve to prevent the
backflow of vacuum pump oil into the refrigerant system.
● Pressurize system with 600 PSI Nitrogen.
● System must hold 600 PSI for a minimum of 24 hours.
● Calculate additional refrigerant charge. Add additional
refrigerant with R410A gage manifold and hose.
● Do not connect to the power source.
● Use copper tube of the specified material and thickness to
meet endurance pressure of the pipe. (609 psi (4.2 MPa))
● Do not use pipe with dust and dirt sticking to it during piping
connection work.
● Always flow dry nitrogen through piping while brazing.
Preparations
Start of work