1-4. TRANSPORTATION THE OUTDOOR UNIT
HOISTING METHOD
When hanging the outdoor unit and conveying it to installation location, hang the unit with rope by passing
through the 4 opening holes on bottom of front and rear side as shown in figure.
Use 2 ropes at least 26ft. (8m) long. If a shorter length is used, it may cause damage to the unit.
Use a rope strong enough to support the weight of the unit.
Use protective boards, pads or tarps to protect the unit from being damaged by the lifting ropes.
Keep the unit level while lifting.
Lift carefully and protect the unit from any mechanical shock.
Protective boards
Opening hole
Model name Weight lbs. (kg)
AOUA72TLBV
597 (271)
AOUA96TLBV
AOUA120TLBV 639 (290)
LIFTING BY FORKLIFT
When using a forklift to move the unit, place the forks in the pallet as shown below.
Front : Bottom of the wooden delivery pallet.
Side : Space between pallet and cabinet. (Enable to remove the pallet from cabinet.)
The unit is removed from the pallet from the side.
Be careful not to damage the unit.
LIFTING BY FORKLIFT(Manual forklift: Pallet Jack)
When using the manual forklift to lift the unit, pass the forks through to the opening space between pallet and
cabinet from side.
Fork (forklift)
Front Side
Fork (forklift) or Fork
(Manual forklift)
Delivery pallet