Design and Technical Manual

6. SYSTEM DESIGN
ADDITIONAL CHARGE CALCULATION2-5.
The outdoor unit is charged refrigerant at the factory.
Additional refrigerant required to be charged on site depending on pipe length.
The additional refrigerant charge amount is calculated according to the following formula.
Round up the calculated result to two decimal places.
CALCULATION OF ADDITIONAL CHARGE REFRIGERANT
Diameter of liquid
pipe
unit: in. (mm)
Additional amount for
pipe length
unit: oz./ft. (g/m)
ø1/4 (6.35) 0.224 (21)
ø3/8 (9.52) 0.624 (58)
Calculation of additional amount for pipe length
z
Total
length of
ø3/8in.
(9.52mm)
liquid pipe
x 0.624
oz./ft.
(58g/m)
ft (m)
oz. (g)
Total
length of
ø1/4in.
(6.35mm)
liquid pipe
x 0.224
oz./ft.
(21g/m)
ft (m)
oz. (g)
+ = =
Total
oz. (g)
Total
lbs (kg)