6.1
Commissioning
In this section:
6.1.1 Apply Power to RU
6.1.2 Complet e RU Installation
6.1.3 Radio Commissioning
Prior to commissioning the RU, the following crit eria must be complet ed:
Circuit breaker is off prior to connecting the RU
All cables at RU connected and terminat ed
Optical SFP installed
Ant enna connection is complete
Important: The RU does not have a power switch. DC pow er on/ off is cont rolled by the circuit
breaker of the DC pow er source. The circuit breaker must be off when connecting the RU.
Note: The RU requires approximat ely 10 seconds to fully power up.
Commissioning an RU has the follow ing environmental requirement s:
Keep the temperature and humidit y wit hin the specified conditions.
Do not place around objects t hat obstruct the flow of air.
Do not input optical signals higher than the maximum received light level to the optical interface. The opt ical
received may be damaged.
Do not submerge or bury in snow
6.1.1
Apply Power to RU
This procedure describes how to power up the RU.
Prerequisites:
Torx driver
RU mounted and not powered up
Available –48V power cable
Operations
Commissioning
103
Release 1.0 · Issue 1, M arch 2021
Fujitsu and Fujitsu Customer Use Only