Installation Manual
6
Prepare for installation cont...
REV_A02
Looking from the front of the Drawer System, loosely secure a D-ring (Item 4) supplied with SSDR010 to
the top of each first support pillar using a M6 x 20 Hex Bolt, M6 Spring Nut and M6 x 19 Flat Washer
(Items 5, 6 & 7) supplied with SSDR10 as shown below.
()
G
(
H
)
90 mm
Drill 6.5 mm Hole here
either side of Load Bay
Tailgate
Tailgate
Working at the front of the load bay, make a mark on either side of the load bay, 160 mm in from the rear
of the load bay and 90 mm in from the side of the load bay. Drill a 6.5 mm hole on each of your markings
Front of Load Bay
160 mm
Front of Load Bay