Installation Manual
3
FIT YOUR side RAILS
Slide five M8 Nyloc Nuts (Item 3) dome side
down into the U-channel that runs down each
side of the Rack through the gap in the corner
of the Rack as shown to the right. Due to the
j
oint in the Rack you will need to slide three
nuts from one corner and two nuts form the
opposite corner as shown. Position the five nuts
each side as indicated by the balloons.
() A
REV_A01
Place one End Piece and the Joiner Pieces (Items 2, 5) onto either side of the Rack, making sure that the
"Feet" of the End and Joiner Pieces sit inside the U-channel as shown. Line up the mounting holes in the
End and Joiner Pieces with the Nyloc Nuts inserted in Step 2A and loosely secure them to the Rack using
the M8 x 25 Button Head Bolts (Item 1) supplied.
( b )