7.6 System Start up
· When the grid connected system is started, the inverter should be turned on first to avoid the current
pulse of the inverter increasing to the battery pack.
· All installation and operation must comply with local electrical standards.
· Check all power cables and communication cables carefully.
1. Turn on the POWER switch
· After powering on, all the green lights flash once, and then the running water lights flash once. The
light on the Mira-HV25 comes on after a delay, not at the same time as the light on the BMS.
2. Module address assignment
· If the system is powered on for the first time, Mira-BMS will automatically assign the module address
of Mira-HV25 without manual configuration.