Installation Guide
7
Grounding Wiring
Screw the ground screw with screwdriver as shown below.
1. After checking all connections are correct, turn on the external DC /AC
breakers.
2. Turn the DC switch to “ON” position.
3. lnverter will start automatically when PV panels generate enough
energy. The LED will be green and the LCD screen will display the main
interface.
Note:
· When starting the inverter for the first time, the country code will be set
by default to the local settings. Please check if the country code is
correct.
· Set the time on the inverter using the button or by using the APP.
Startup Procedure