Please follow the following steps to mount
the eFlex in a 19” server rack.
1. Ensure your shelf mounts are
properly secured
2. Optional: If you choose to use the
stabilizing brackets, affix those to
the eFlex using T-slot bolts
3. Slide the eFlex onto the shelf mount
4. To connect the terminals to the
inverter, a busbar for the positive
and negative leads (either in the
front or in the back) is recommended
a. Please refer to the rack
installation manual for more
information
Server Rack [Rack Unit]
Useable Depth [Inch]
eFlex Height [Inch]
Quantity of eFlex
18U
≥24
7.20
4
21U
24
7.20
4
27U
24
7.20
6
35U
24
7.20
8
40U
24
7.20
9
45U
24
7.20
10