Installing the Power Recorder at a Facility
15
WCaution
Make sure the current clamps and voltage probes are paired
correctly. The leads for the current clamp and voltage probe of
the same color should be attached to the same phase wire or
busbar.
3. Connect the Recorder to the wiring by first connecting the ground probe to the
distribution system ground, and then the neutral probe to neutral.
4. With the ground clamp to the distribution system ground and the neutral clamp to
neutral connect the current clamps.
5. Connect the remaining current clamps.
• The arrow on the clamp should point toward the load.
• Use the color-coding on the leads to help you connect the probes to the
correct phases, neutral and ground.
6. Connect the remaining voltage probes.
Note
Make sure the voltage probes and current clamps are paired correctly.
Calculations are made in pairs and cannot be changed after data is
recorded. The leads for the voltage probe and current clamp of the same
color should be attached to the same phase wire or busbar.
7. Check the LED for each phase to make sure a connection is established.
• When a phase LED is ON or lighted, you know that the connection is
active and that voltage and current is within the normal range.
• When a phase LED is BLINKING, you are connected but the voltage or
current is exceeding the normal range or exceeding the range of the
probe that you are using.
• When a current LED is OFF or unlit, there is insufficient current present
in the line.
Verifying Your Connection
Before you leave the Recorder to accumulate data at the facility, double-check the
connections.
• Make sure the current clamps are secured and completely closed around the
conductors and that the voltage and current LEDs are steady-on.
• Use the PHASOR screen on the PDA to verify that the voltage and current
connections are correct. You can swap the connections using Power View if they
are incorrect.
Finishing UP
After making any corrections to the connections, recheck the PHASOR diagrams to
confirm your connection. Make sure the nominal voltage, nominal line frequency, and
power type (delta, wye, other) are correct before you leave the Recorder. It is a good
practice to insert a Start Mark when you are finished with all settings so you can
download data and ignore useless readings and events common at the beginning probe
connecting activities.