Installation & Assembly
LVP CLICK
INSTALLATION GUIDE
P a g e | 3
PH LEVELS:
pH on concrete substrates must be between 7 and 9.
STORAGE AND HANDLING:
Acclimate the flooring a minimum of 48 hours before installation in the area it
is to be installed. Conditions between 65°F and 85°F (18°C and 29°C) are
required before, during and after installation. Cartons should be evenly stacked
no more than two high on a flat surface and away from any heating/cooling
ducts or direct sunlight.
The floor must be clean, smooth, flat and dry. Remove all foreign substances
such as wax, grease, dirt, construction marks and contaminants, and any
substance or chemical that would interfere with a good bond. Avoid using
sweeping compounds. Do not install over substrates that have been chemically
cleaned. The flatness of wood subfloors or underlayment must not exceed on
variation of 3/16” in 10 feet.
Please Note:
If removal of existing resilient floor covering is required, follow all
recommended Resilient Floor Covering Institute (RFCI) work practices at
www.rfci.com The Manufacturer only recommends the use of Portland cement
based products as a satisfactory patching or leveling compound for the
installation of all The Manufacturer flooring products.
COMMON USES:
Leveling Substrates
Filling holes
Filling cracks
Embossing existing resilient floor, ceramic tile of VCT
Leveling non water-soluble adhesives
Filling saw cuts and/or construction joints
WARNING:
For installation over old resilient floor coverings or when considering removing existi ng resilient
floors, please be advised that these products may possibly contain asbestos fibers or crystalline
silica. Please follow all recommended Resilient floor Covering Institute (RFCI) work practices at
www.rfci.com.