User's Manual
Table Of Contents
- toc
- Issue Date: 09- 23- 2003
- Overview
- 1.1. Installation Equipment
- Verifying the Site Preparation
- 2.1. Site Preparation Checklist •24 Outdoor BaseStation
- 2.2. Preparing the Floor
- Installing the Cabinet
- Connecting the Power System
- Connecting the Core Network Cables
- Connecting the Antennas
- Powering Up the Cabinet
- Powering Down the Cabinet
- Verifying the Installation
- RadioRouter Outdoor BaseStation Site Preparation Punchlist
- Outdoor BaseStation Installation Punchlist
- tables
Page 35
Chapter 9. Verifying the Installation
Verifying the proper installation of the cabinet must be done before the installation can be
considered complete.
Verify all of the following items:
1. Clearance requirements are met — at least 24” front, 12” side, and 24” rear. There must be
room to open the cabinet doors for service.
2. The base station is powered up. All the LEDs in Table 7.1 Power On Expected LEDs must
reflect the states listed in the table. The system should remain in the powered up state. If it
is necessary to power down the base station, do so only in accordance with the instructions
in Chapter 8. Powering Down the Cabinet.
3. Correct terminations on all T1 cables.
4. No kinks in RF cables.
5. RF cable markings match those specified in Chapter 6. Connecting the Antennas.