User's Manual

Table Of Contents
Page 17
4.
Connect the ground cable to the connectors with 6 to 2 AWG wire with a 2–hole lug for a
1/4” diameter stud. See Figure 4.6 Main Ground with Cable.
Figure 4.6 Main Ground with Cable
5.
Fasten the l ug on to the stud with the nuts provided. Tighten nuts to 40–50 in-lb torque.
6.
Connect the other end of the cable to the Master Ground Bar or other suitable ground
source available at the installation site.
7.
Reinstall the Roxtec seal inserts and outer panel after all of the system cables have been
routed. The seal inserts are installed tight against each cable and are held in place when
the outer panel is installed. See Figure 6.4 Cables Installed in Cabinet.
RadioRouter
®
BaseStation Installation Guide Draft
Version 0.2 - © 2003 F larion
Flarion Confidential
Page 17