User's Manual
Table Of Contents
- toc
- Issue Date: 09- 23- 2003
- Overview
- 1.1. Installation Equipment
- Verifying the Site Preparation
- 2.1. Site Preparation Checklist •24 Outdoor BaseStation
- 2.2. Preparing the Floor
- Installing the Cabinet
- Connecting the Power System
- Connecting the Core Network Cables
- Connecting the Antennas
- Powering Up the Cabinet
- Powering Down the Cabinet
- Verifying the Installation
- RadioRouter Outdoor BaseStation Site Preparation Punchlist
- Outdoor BaseStation Installation Punchlist
- tables
Page 14
Procedure 4-2 Connecting the Power Cable
1.
Locate the AC power connection points in the Load Center. See Figure 4.3 Load Center
Connections.
Figure 4.3 Load Center Connections
2.
Connect the power cable to the screw terminals for Neutral, Ground, Line 1, and Line 2.
Use #12 AW G wire or heavier.
3.
Connect the other end of the cable to the AC power source in the Service Entrance.