User's Manual
Table Of Contents
- toc
- Issue Date: 09- 23- 2003
- Overview
- 1.1. Installation Equipment
- Verifying the Site Preparation
- 2.1. Site Preparation Checklist •24 Outdoor BaseStation
- 2.2. Preparing the Floor
- Installing the Cabinet
- Connecting the Power System
- Connecting the Core Network Cables
- Connecting the Antennas
- Powering Up the Cabinet
- Powering Down the Cabinet
- Verifying the Installation
- RadioRouter Outdoor BaseStation Site Preparation Punchlist
- Outdoor BaseStation Installation Punchlist
- tables
Page 9
8.
Slide the battery tray out completely. See Figure 3.4 Battery Tray Open.
Figure3.4BatteryTrayOpen
9.
Remove all four cabinet to pallet mounting bolts. You may have to access the front bolts
from the rear access panels.
10.
Close the battery tray.
11.
Lock the tray and replace the two screws.
12.
The cabinet is now ready to be moved into place.
RadioRouter
®
BaseStation Installation Guide — Draft
Version 0.2 - © 2003 F larion
Flarion Confidential