User's Manual

Verifying the Installation
Chapter 10. Verifying the Installation
Verifying the proper installation of the cabinet must be done before the installation can be
considered complete.
Verify that all of the following re quirements are met:
Clearance re quirements are met at least 24” front and 6” rear. There must be room to open
the cabinet doors for service .
The base station is powered up. All the LEDs in Table 8 .1 Power On Expec ted LEDs must
reflect the states listed in the table. The system should rema in in the powered up state. If it is
necessary to power down the base station, do so in accorda nce with the instructions in Chapter
9. Powering Down the Cabinet.
Correct terminations on all T1 and alarm cables
No crimps in RF cables
RF cable markings match those specified in Chapter 7. Connecting the A ntenna Cables.
© 2005 Flarion
Flarion Proprietary and Confidential
Version 1.7
Page 10-1