User's Manual
Table Of Contents
- toc
- Issue Date: 08- 04- 2003
- Overview
- Verifying the Site Preparation
- 2.1. Site Preparation Checklist •24 Indoor BaseStation
- 2.2. Preparing the Floor
- Installing the Cabinet
- Connecting the Power System
- 4.1. Routing the Cables
- 4.2. Connecting to Power and Ground
- Connecting the Core Network Cables
- Connecting the Antennas Cables
- Installing the Alarm Connections
- Powering Up the Cabinet
- Powering Down the Cabinet
- Verifying the Installation
- 10.1. Verifying the Physical Installation
- 10.2. Verifying the Base Station Operation
- RadioRouter BaseStation Site Preparation Punchlist
- RadioRouter BaseStation Installation Punchlist
- tables
Page 2
ESD CAUTION:
It is the r esponsibility of the installer to ensure that all necessar y
precautions are taken to avoid electrostatic discharge damage to the
equipment.
Note:
All installation work must be coordinated with the carrier to insure compliance with carrier require-
ments regarding scheduling work during maintenance windows.
In addition to standard installation tools, it is recommended that special equipment be used to
move the RadioRouter cabinet. The following list gives ex amples of equipment which can be
used:
• Pallet jack with 27” width across the jacks. Pallet jack 4YX97 from Dayton or equivalent.
• A 36” L x 24” W x 5.5” H flat equipment dolly. McMaster Carr part number 2730T6 or equivalent.
See Figure 1.1 Flat Equipment Dolly
• Hoist or crane with heavy duty structural straps — 1000 lb load capability
Figure 1.1 Flat Equipment Dolly
RadioRouter
®
BaseStation Installation Guide — Draft
Version 0.5 - © 2003
Page 2