8. While supporting heater, tilt the Head and Upper Post Assembly (B) and
screw in the 3 M8x70 Stud Bolts (BB) into the holes on top of the Head
Assembly. Slide the assembled Reflector over the 3 bolts that now extend from
the Head Assembly. Use the 3 M8 Wing Nuts (EE) and 3 M8 Washers (GG) to
secure the assembled Reflector to the Head Assembly of the heater. Once you
have tightened the Wing Nuts, return the heater to an upright position.
Hardware Used: 3 x EE, Wing Nut M8
3 x GG, Washer M8
9. Connecting the LED feature:
This heater comes equipped with LED rope lights preassembled in the base and Post support plate (See Fig.1 and
2 below):
To connect the LED feature, once the heater is assembled, locate the two connectors—one will be inside the Tank
housing assembly on the right side by the Tank housing door and the other will be at the right front corner at the
bottom of the Post support pate. The LED control box is located on the back side of the Tank housing door (NOTE:
Before attaching the LED connectors to the LED control box, you must insert a 9v battery by sliding the top of the
LED control box back towards you to release the top. Once the top is removed, insert the 9v battery and then
replace the top by sliding in back on the box away from you.) Connect both sets of connectors and control LED
feature with On/Off switch located on LED control box.
ASSEMBLY
8