Installation Instructions

Level Install: Step 5 – Attach Rail Kits to Posts
a) Insert the rail kit assembly between the posts and slide down onto the RCBs. (see Figure 5.1)
b) Secure the top and bottom rails to the RCBs using two colored #8 x 3/4” screws for the top rail and two
for the bottom rail (see Figure 5.2). Note: Drill 1/8” pilot holes for the screws and offset the holes slightly
so that the screws do not hit one another inside the RCBs. The screws require a #2 square drive bit.
Level Install: Step 6 – Cut and Attach Snap Caps
a) Measure underneath the top rail from the face of the intermediate picket to the adjacent post faces.
(See Figure 6.1)
b) Trim the Snap Caps at the end with the hole to match the corresponding measurements.
c) Position the Snap Caps so the trimmed end is against the post. Press the Snap Caps on to the bottom
of the top rails until they click and lock into place. (see Figure 6.2)
(Figure 5.2)
4
1-800-888-2418 | www.feeneyinc.com
(Figure 6.2)
(Figure 6.1)
Level Install: Step 7 – Install CableRail Infill
See page 5 for more information.
(Figure 5.1)
(COLORED)
(COLORED)