Installation Guide
318267-1
FAST 2K™ DECK POST ANCHOR
Installation Instructions
January 2021
North America
H.B. Fuller | Royal Adhesives & Sealants Canada Ltd
266 Humberline Drive | Toronto, Ontario, Canada M9W 5X1
Tel. +1 416 679 5676 | Fax: +1 416 679 0511 | hbfuller.com
fast2k.com
performance. Material applied at lower temperatures is slower to cure and yields a lower volume. Material applied at higher temperature
provides a very short working time and a lower strength product.
2. Place the post in the hole, ensuring it is vertically plumb and in the desired position. Once the Fast 2K™ Deck Post Anchor is poured
into the hole, the post should only be moved for 10 seconds. Ensure posts can be held for approximately 5 minutes after the installation
of Fast 2K™ Deck Post Anchor. Bracing the post may help ensure its position is correct.
3. Ensure that any standing water present in the hole is less than ½” in depth – when more water is present, water should be removed
with a pump, or have aggregate/soil/cement placed in the hole to increase the base of the hole above the water.
4. Fast 2K™ Deck Post Anchor will adhere to itself, allowing for additional material to be poured into holes that are larger
than a single kit will fill. In the event too much material is used, Fast 2K™ Deck Post Anchor may be trimmed after hardening
for 15 minutes.
5. Fast 2K™ Deck Post Anchor consists of Part A and Part B, and is sold in divided bags, a set of jugs or a set of drums.
Please follow the applicable instructions below:
When installing posts using divided bags of Fast 2K™ Deck Post Anchor
a. Have a pair of scissors or a knife readily available. Mix immediately beside the area of installation.
Have a surface with a hard, round edge (ie: ladder, sawhorse, round metal post, etc.) available for mixing.
b. DO NOT EXCEED THE STATED MIXING TIME AND DO NOT ALLOW MATERIAL TO START EXPANDING INSIDE
THE BAG.
c. Release the clip from the bag by moderately pulling the bag outwards from the clip.
d. Rub the bag with moderate force along a hard, round edge by forcing the material inside the bag from one end to the other
with each stroke (“shoe shining” technique). Mix for 30 seconds.
e. Use the tear notch, or an available knife/scissors to open the bag and immediately pour Fast 2K™ Deck Post Anchor
into the hole.
f. Applying Fast 2K™ Deck Post Anchor on the post on all sides will help reduce the amount of water that will contact the post.
g. Rolling the bag will help completely empty the content into the hole.
h. After installation of Fast 2K™ Deck Post Anchor has begun, do not lift the post and complete adjustments to placement
within the first 10 seconds.
When installing posts using jugs of Fast 2K™ Deck Post Anchor
a. Affix the provided mixing blade to a handheld electric drill.
b. Mix immediately beside the area of installation.
c. DO NOT EXCEED THE STATED MIXING TIME AND DO NOT ALLOW MATERIAL TO START EXPANDING INSIDE
THE JUG.
d. Pour the entire contents of Component B into the larger Component A jug.
e. Insert the mixing blade and mix for 30 seconds.
f. Immediately pour Fast 2K™ Deck Post Anchor into the hole.
g. Applying Fast 2K™ Deck Post Anchor on the post on all sides will help reduce the amount of water that will contact the post.
h. After installation of Fast 2K™ Deck Post Anchor has begun, do not lift the post and complete adjustments to placement
within the first 10 seconds.