2: Connections to the weighbridge are installed by drilling a hole in the welded flange (stiffen-
er). Scrape / sand enough paint / coating away to make a good electrical connection and
secure with the provided hardware.
3: Connect the strap to the weighbridge steel using the provided set screw terminals and
coat with grease AFTER the connection has been made.
4: Ground rod #3 should be located near the interface conduit. It is used to connect to the
isolated ground of the Pit Power Supply (PPS) Acc 2001-1 only.
5: The Junction Box Plate MUST be connected to the weighbridge with a ground braid, or a
conductor of not less than 10 AWG.