GENERAL ASSEMBLY INSTRUCTIONS
1. Build the top two full height sidewall rings.
2. Install the tension angle segments.
3. Locate the signs and install the top set of 2 ring stiffeners.
4. Fasten the plenum rafters to the tension angle and center collar.
5. Space the plenum rafters with the plenum sheet and plenum rafter supports
6. Pre-install the dump hoppers and flashing to the plenum roof sheets.
7. Locate all plenum roof sheets and tighten all bolts.
8. Place all of the grain bands on the plenum floor.
9. Install the top half sidewall ring.
10. Assemble the roof to the top sidewall half ring.
11. Fasten the dump chutes, chain, pulleys, etc. to the Ezee Dry unit, and string the dump
chute lift cable through the sidewall.
12. Install all the grain band rings and flashing sealer plates.
13. Lift the bin and add the third and fourth full sidewall rings, bolting the fan entrance
frame into position.
14. Assemble the platforms.
15. If the bin utilizes Vac-u-vents, bolt the upper rod section to the roof.
16. Continue building the bin by adding sidewall sheets, stiffeners and ladder.
17. Install the door into the 2nd ring (1 ring door) or 2nd & 3rd rings (2 ring door).
18. At the base of the bin install the base angle, connectors, clips and keepers. Seal the bin
to the concrete.
19. Field cut the bottom ring for the aeration transition.
20. Assemble the floor using the instructions in the floor bundle.
21. Install the winch (batch unit) or hydraulic pump unit (continuous flow) and the controls.