015886 5-02
50 (batch units only)
fasten the winch and winch bracket
Install the winch bracket and winch roughly
48” above the concrete as shown in figures
a and b. Trim the cable as needed and attach
it to the winch. The travel of the cable must
be limited to prevent damage to the dump
hoppers. After insuring that all dump chutes
are level, attach a cable clamp to the cable
as close to the winch drum as possible. This
clamp acts as a visual indicator of when to
stop raising the dump chutes. Release the
cable from the winch until this clamp is
approximately 30” above the winch drum
and attach a second cable clamp to the cable
beneath the outer pulley bracket near the
top of the bin sidewall. This clamp prevents
over-opening of the dump chutes. Make sure
that the chains are tight so that the chutes
don’t interfere with the hopper neck when
in the lowered position.
51
install hydraulic pump unit
Install the hydraulic pump unit along with
the cylinder / accumulator assembly as
shown in figure c. Trim the cable and attach
it to the cylinder using two cable clamps.
Connect the hose between the pump unit
and the cylinder. Field drill all holes.
(continuous flow /
automatic batch units)
INSTALL THE WINCH
a
bin wall
outside pulley
brackets
cable clamp to
limit downward
travel of spouts
cable clamp
cable stop
winch
30”
ADD THE HYDRAULIC PUMP UNIT
c
36”
24”
pump unit field drill holes
cable
cylinder
accumulator
foot pad
WINCH ASSEMBLY DETAIL DRAWING
b
cable
winch
mounting
bracket
field drill (3) 3/8” holes
NOTE:
Look back at the
pulley brackets illustration and
step 31 on page
46.