Owner`s manual

47
015886 5-02
33
install the chain assemblies
Fix the center chain disk at an elevation
of 3” beneath the pulley bracket (fig. d).
Install “S” hooks in each edge hole of
the disk. Take the twin loop chain and
cut it into equal lengths based on the
chain length chart. Install two lengths
of chain 180º apart, from the “S” hooks
in the center disk to the outer dump
chutes. Adjust the chains until the dump
chutes are level (fig. d). Continue around
the bin installing chain pairs to the upper
dump chute. Use the same “S” hook in
the center chain disk as was used for
the lower dump chute.
INSTALL THE LIFTING CHAIN ASSEMBLY
d
cross braces
4’ long chain
5/16” eye bolt
jack beam
19’ long chain
3’ long chain
3”
up position
down position
dump hoppers
and chutes
truss
upper plate is for inner
spouts with 13’ long
chains (place one chain
every other hole)
place lift plates far
enough apart in the
closed position so that
the upper plate may be
lowered without hitting
the lower plate
NOTE: 3/8” diameter hole for the eyebolt is
located above the 19’ chain and is drilled in
the field. Eye bolts must be double nutted.
Broken lines show system in the open or
down position. A 3” clearance on the cross
braces is to be maintained with the grain
spouts in the down position.
NOTE: for clarity not all
detail is shown.
center collar
down position