Owner`s manual

25
015886 5-02
1
set out bin sidewall sheets on the pad
Sort the sidewall sheets by gage
according to the color code and
layout table (page
59). Stand the
sidewall sheets on edge in the order
in which they will be used on the bin
pad near the location where the
sidewall will be built.
FOR BINS WITH TWO FAN ENTRANCES
g
ADD THE SECOND RING
e
2
begin sidewall assembly
Build the top three sidewall rings (fig.s
d-g and fig. a, page
26). Refer to the
sidewall layout sheet table on page
59.
Make sure to use the proper number
and style of sheets so the diameter of
the bin is correct. For Ezee Dry bin
door and fan entrance space locations
refer to figures f and g. At the stiffener
locations install 5/16” x 1” bin bolts
in the “inside corrugation valleys” of
the vertical sheet seams at this time
(see fig. b on page
27). Stiffener bolts
will be added later in the “inside hill”
holes of the sheets.
BUILD THE TOP SIDEWALL RING
d
FOR BINS WITH ONE FAN ENTRANCE
f
no stiffener hole punching on the 1st ring
dryer assembly hole
punching on the 2nd ring
17 gage 10 gage
15 gage
15 gage
one fan entrance
door
two fan entrances
door