Ezee Dry Assembly
GENERAL ASSEMBLY INSTRUCTIONS
1. Complete the foundation. See the foundation section earlier in this manual.
2. Set the sidewall sheets out near the pad in preparation for assembly.
3. Plan for the ladder location.
4. Bolt together the top three rings of the bin.
5. Connect the top 10 gage z-bar stiffeners to the vertical seams of the
second sidewall ring (10 gage).
6. Using scaffolding or a stand, support the center ring assembly at the
proper height.
7. Install the main trusses.
8. Add the stiffener tie rods.
9. Attach the jack beams between all main trusses.
10. Fasten the mounting brackets to the sidewall and bolt the intermediate
purlins to the mounting brackets.
11. Install 10 gage skirt sections at the upper bottom side of the main trusses.
12. Secure the pulley angle to the center collar.
13. Connect the cross braces to the vertical angles of the main trusses.
14.
Attach the dump hoppers, dump necks, and flashing to the perforated roof sheets.
15. Add the perforated roof sheet assemblies to the structure.
16. Bolt on the flashing between perforated roof sheets and the sidewall.
17. Attach the upper perforated skirt and center cone to the assembly.
18. Install the eave clips and support the peak ring on a stand at the proper height.
19. Fasten on the roof sheets, complete the roof, and assemble the manway door.
20. Assemble the grain band rings.
21. Attach the 68’ cables and the chains to the center chain disks.
22. Build on the fan platform(s).
23. Complete the sidewall, adding the z-bar stiffeners as construction progresses.
24. Install the base angle and secure the bin to the anchor bolts.
25. Assemble the hydraulic pump unit if the bin comes equipped with one.
26. Add any other optional equipment included with the bin and finish construction.
NOTE:
Look over the ladders
sections of this manual on
pages 42 - 43 and 60 - 63
before building the bin. It
offers important information
for planning the bin’s layout
and construction.
Assembly