Assembly Instructions
Pre-sizing and Cutting Top and Bottom Rails 
(prior to assembly):
1.  Measure the distance between your posts from the inside edge of the
  post to the inside edge of the other post. Ensure the measurement is
  the same at the top and at the bottom of the posts (IIlustration #1). 
  If the measurements are different, your posts may not be level and 
  may need to be shimmed. 
  2.  Cut both top and 
    bottom rail sections 
   ½" shorter than your 
   measurements, 
    assuring they will 
    pass between the 
    posts without 
    scratching the post’s 
    surface during 
   installation.
Top and Bottom Rail Installation:
1.  Place a short cut of 2"x4" lumber on edge near each post 
  perpendicular to the railing direction. (Illustration #2)
2.  Slide mounting brackets (C) on each end of the bottom rail.
3. Setthebottomrailsection(withbracketsoneachend)ontothe2”x4”’s
  and between the posts. The 2x4's will provide the proper 3 1/2" gap 
  below the bottom rail. 
4.  Centering the bottom rail bracket from each edge 
  of the post, fasten it using the 7/8" self-drilling 
  fasteners (E) for EZ Posts or 2" SMS fasteners (F) 
  for wood posts.IMPORTANT: Once the brackets are 
  secure on the posts, fasten the bracket and rail together 
  using a 7/8" self-drilling fastener. Drilling a pilot hole 
  with an 1/8" bit and fastening on the non-visible 
  side is preferable. (Illustration# 2).
5.  Measure from the decking up the post to 36 ¼" for 
  residential and 42 ¼" for commercial railing 
  make a pencil mark at the center of the post. 
  Repeat process at the opposite post. (Illustration #3)
6.  Slide mounting brackets onto both ends of your top 
  rail (flat surface up) and hold the top of the top rail 
  in place at your pencil marks. (Illustration #3.5)
7.  Using a baluster (C) test that the vertical spacing 
  between the rails, allows the baluster fasteners 
  holes to center on the railing fastener line. 
  (Illustration #4)
Illustration #2.5
(J)
(D)
Spacing is not to exceed 3 3/4" from the 
bottom rail to the deck.
Predrill using 
a 1/8" pilot hole. 
Illustration #1
Illustration #3
Illustration #7
Note: A&B are 
identical pieces
(A)
(B)
8.   Holding the top of the bracket at your pencil mark, level 
  the top rail and fasten each bracket to your posts using 
  the appropriate fasteners provided (same fasteners 
  as the bottom rail). (Illustration #5)
9.  Once the brackets are secure on the posts, fasten the 
  bracket and rail together using a 7/8" self-drilling 
  fastener. Drilling a pilot hole with an 1/8" bit and 
  fastening on the non-visible side is preferable.
Baluster Infill spacing:
To determine symmetric baluster spacing for your 
railing section, REVIEW APPENDIX A and follow 
the steps below.
1.  Determine your preferred baluster spacing from Appendix A. We recommend 
 using Method 2: Decks.com Baluster Calculator www.decks.com/calculators/ 
 baluster-spacing.Also,werecommendthe“spacewidth”(distancebetween
 balusters)tobe3¾”.However,ifthiscausesthe“outsidespace”tobe
  greatly different than the baluster spacing, try smaller spacing calculations 
 foramoreuniformlook(e.g.31/2”).(Illustration #6)
2. Ifyourbalusterspacingisdifferentthan3¾”,cuttheincludedSpacer(F)
  to your new spacing width. 
3.  Using the results from your decks.com calculations and the Spacer (F), 
  temporarily space the balusters to verify the overall layout. Start by stretching 
  your tape measure across entire bottom rail.
4.  Make on-center marks (from decks.com calculator) 
  or use small pieces masking/painters tape on the 
  top vertical leg of the bottom 
  rail from left to right. 
5.  Verify if there are any height
  variations of the balusters. This 
  is common. Move the shorter 
  length balusters to the middle 
  locations as they will be 
  installed first.
Installing the balusters:
1.  Place the middle (shortest baluster) in its on 
  center mark spaced location and in between the top and bottom rails.
2.  At the bottom hole of the baluster, mark the center 
  of the fastener hole using a punch or awl.
3. Atyourpunchmark,drilla3/16”pilothole
  into the bottom rail using the included drill bit.
4.  Secure the baluster to the bottom rail using a 
 5/16”hexbitanda7/8”fastener(E).
5.  Level the baluster vertically. Double check with a 
  horizontal measurement from the post to the edge 
  of baluster at the top and bottom rails.
6.  Set next baluster in place to the left using the 
  Spacer (F). Use the Spacer at both the top and 
  bottom rail.
7.  Verify baluster is aligned with the on-center marks 
  on the bottom rail.
8.  Punch bottom fastener location, drill pilot hole 
  and secure bottom of baluster with fastener.
9.  Punch top fastener location, drill pilot hole and secure top 
  of baluster with fastener.
10.  Repeat installing balusters on the left side and repeat from middle 
  to the end of the right side.
Illustration #6.5
Illustration #4
3 3/4"
Illustration #3.5
Illustration #5
Illustration #6
Illustration #2