User Manual
2-5
PoleVault Systems Installation • Installation — Stage 1
4. Cut the ceiling tile
a.  Mark the location of the PCM 240 on the T-bar, before 
removing it. This aids putting it back in the correct 
location when the tile is replaced.
T
 Mark the screen direction on back of the tile (e.g. with 
an arrow or “to front”) to help orientation of tile when 
replacing it after cutting.
b. Measure the distances X and Y (see gure) from the inner 
vertical section of the front and left T-bar runners to the 
center of the Pipe Adapter Plate.
c.  Using these dimensions, mark and cut a hole for the 
PMP in the ceiling tile.
T
  Place the tile on a box, mark the hole’s center on the 
underside of the tile. Use a hole saw bit to start to cut 
the hole by hand (turning bit counter clockwise) to 
avoid damaging the tile. When the drill bit is through 
the tile, turn the tile over and finish cutting from the 
top side.
5. Finish Projector Ceiling Mount 
installation
a.  Loosen the set screws and unscrew the UPB 25 from the 
mounting pole. Do not remove the projector bracket 
from the projector.
b. Loosen the PCM 240 ‘s set screw and remove the 
mounting pole, then remove the PCM 240.
c.  Replace the cut ceiling tile, checking the orientation to 
align the hole with the PCM 240.
d. Replace the PCM 240 over the ceiling tile and screw 
the mounting pole (with the access hole uppermost) up 
through the hole into the mounting plate. Tighten the set 
screws.
T-bar
X"
Y"
Minimum and
Maximum
Throw Distance Marks
4b
 Take measurements with the PCM 240 
 on the T-bar
5d
 Screw the PMP into the mounting plate  
 (viewed from below)
4c
 Mark and start cutting the hole on the 
  underside. Finish on the top side.