Manual
Outline of Installation Steps for PlenumVault Digital Systems (PVM 220)
Stage 1 — Install the Screen and Projector.
c Mark the screen location (page 18).
c Install projector to verify location (page 18).
c Verify the image location (page 21).
c Cut the ceiling tile (page 22).
c Preliminary safety hardware installation (page 22).
c Finish projector drop ceiling mount installation (page 23).
c Secure the projector drop ceiling mount to the ceiling (page 24).
c Install the electrical box (if required) (page 25).
c Install the screen (page 25).
Stage 2 — Mount the PVT Wall Plates and the MLC 104 IP Plus.
c
Install the mud rings (page 29).
c Pull cables (at the input locations) (page 30).
c Install the wall plates (page 31).
c Install the MediaLink Controller (page 32).
Stage 3 — Install the FF 120 Speakers.
c Cut the ceiling tile (page 36).
c Install the speaker on the drop ceiling (page 36).
c Terminate the speaker cable for the PVS switcher (page 38).
Stage 4D — Install the PVM 220 and PVS 405D.
c Remove the device mounting plate from the access door (page 53).
c Remove ceiling tile and install suspension cables (page 53).
c Suspend the main PVM 220 enclosure from the ceiling (page 54).
c Run AC power wiring to the AC module in the PVM 220 (page 55).
c Run signal and control cables to the PVM 220 (page 56).
c Install devices onto the device mounting plate (page 57).
c Cut and install ceiling tile into the access door (page 57).
c Install the mounting plate onto the access door (page 58).
c Cable the switcher (page 58).
c Verify and configure the setup (page 59).
c
Attach the door tether to the door (page 59).
c Secure the door latches (page 59).
Stage 5 — Configure the PoleVault Switcher and the System.
c Configure the switcher — PCS Configuration program (page 61).
c Configure the system — Global Configurator (page 62).
c Test the system (page 63).
c Final installation (page 65).
PoleVault Digital Systems • Installation Overview 75