Outline of Installation Steps for PlenumVault Digital Systems (PVM 220)
Stage 1 — Install the Screen and Projector.
c  Mark the screen location (page 18).
c  Install projector to verify location (page 18).
c  Verify the image location (page 21).
c  Cut the ceiling tile (page 22).
c  Preliminary safety hardware installation (page 22).
c  Finish projector drop ceiling mount installation (page 23).
c  Secure the projector drop ceiling mount to the ceiling (page 24).
c  Install the electrical box (if required) (page 25).
c  Install the screen (page 25).
Stage 2 — Mount the PVT Wall Plates and the MLC 104 IP Plus.
c
  Install the mud rings (page 29).
c  Pull cables (at the input locations) (page 30).
c  Install the wall plates (page 31).
c  Install the MediaLink Controller (page 32).
Stage 3 — Install the FF 120 Speakers.
c  Cut the ceiling tile (page 36).
c  Install the speaker on the drop ceiling (page 36).
c  Terminate the speaker cable for the PVS switcher (page 38).
Stage 4D — Install the PVM 220 and PVS 405D.
c  Remove the device mounting plate from the access door (page 53).
c  Remove ceiling tile and install suspension cables (page 53).
c  Suspend the main PVM 220 enclosure from the ceiling (page 54).
c  Run AC power wiring to the AC module in the PVM 220 (page 55).
c  Run signal and control cables to the PVM 220 (page 56).
c  Install devices onto the device mounting plate (page 57).
c  Cut and install ceiling tile into the access door (page 57).
c  Install the mounting plate onto the access door (page 58).
c  Cable the switcher (page 58).
c  Verify and configure the setup (page 59).
c
  Attach the door tether to the door (page 59).
c  Secure the door latches (page 59).
Stage 5 — Configure the PoleVault Switcher and the System.
c  Configure the switcher — PCS Configuration program (page 61).
c  Configure the system — Global Configurator (page 62).
c  Test the system (page 63).
c  Final installation (page 65).
PoleVault Digital Systems • Installation Overview 75