User`s manual
Cable Cubby
®
Products • Installation
Installation, cont’d
2-8
Cable Cubby
®
Products • Installation
2-9
Installing the power module (CC 300, 600, and 800)
From the underside of the Cable Cubby, gently push the power
module into the desired position at the desired elevation. Secure
the power module into position with four Phillips head screws.
N
The Universal AC outlet is fully compatible with
Europlug, British, Indian, Danish, and Italian plug
types. See the universal AC outlet guide on the Extron
Web site, www.extron.com, for compatibility details on
all plug types.
Installing the cables
Three half-moon cutouts in each set of cable pass-through (split)
AAPs loosely channel three cables in the Cable Cubby. Each
channel is padded with a split grommet to prevent cable wear.
Each channel and each associated split grommet is a different
size (gure 2-5).
Large
Medium
Small
Large
Medium
Small
Large
Medium
Small
Cable hole Hole sizeGrommet size
Large 0.625" (1.59 cm) 0.453" (1.15 cm)
Medium 0.562" (1.43 cm) 0.390" (0.99 cm)
Small 0.5" (1.27 cm) 0.312" (0.79 cm)
Figure 2-5 — Cable pass-through AAPs
A typical installation consists of a VGA cable, an audio cable,
and a network cable. In a typical installation, the VGA cable
runs in the largest channel, the network cable runs in the middle
(medium) channel, and the audio cable runs in the smaller
channel. In a non-standard installation, just match the diameter
of the cable to the size of the channel as best you can.
Install cables in the channels as follows:
1
. Remove a segment of a set of split AAPs by unscrewing
the nuts on the underside of the bracket that fastens the
plate to the shelf (CC 200) or shelf bracket (CC300, 600, or
800). See gure 2-4, on page 2-7.
2. Rest the cables in the half-moon cutouts of the split AAP
segment still mounted on the shelf (CC 200) or shelf
brackets (CC 300, 600, and 800). Place the cables so that
the connectors that require inside Cable Cubby access
protrude from the front (black side) of the split AAP
segment.
3. Insert the screws of the split AAP segment that you
removed in step 1 through the holes in the shelf bracket.
Ensure that the cables are free in the channels that the two
split AAP segments form without being pinched where the
two segments meet.
4. Secure the split AAP segment to the shelf (CC 200) or shelf
brackets (CC 300, 600, and 800) with the provided captive
washers and #4-40 nuts.
5. Slip the appropriate
size split grommet
over each cable with
the ange of the
grommet toward the
connector that will be accessible
inside the Cable Cubby. Snap
the grommets into the channels.
6. If applicable, snap the included
hole plugs into unused
channels in place of the split
grommets.
Installing the AAPs
The split AAPs can be replaced with passive Extron AAPs.
Replace a set of split AAPs as follows:
1. Remove the set of split AAPs to be replaced by unscrewing
the nuts on the underside the shelf (CC 200) or shelf
bracket (CC 300, 600, and 800) that fasten the plates to the
bracket (gure 2-4, on page 2-7).
2. Cable the rear of the AAP(s) to be installed before attaching
the AAPs to the enclosure.
3. Insert the screws of the AAPs through the holes in the shelf
or shelf bracket. Secure the AAPs to the shelf brackets with
the provided captive washers and #4-40 nuts.