Installation Instructions
Table Of Contents
- Notices
- Safety messages
- Before you begin
- Installing the VSP 4450GTX-HT-PWR+
- Installing the Virtual Services Platform 4000 on a table or shelf
- Installing the Virtual Services Platform 4000 in an equipment rack
- Installing SFP transceivers
- Removing SFP transceivers
- Power specifications for VSP 4450GTX-HT-PWR+
- Virtual Services Platform power supply power specification
- Installing the VSP 4450GTX-HT-PWR+ power supply
- Connecting to AC power
Caution:
Risk of high current and board burn out if battery is replaced by an incorrect type. Dispose of
used batteries according to the instructions.
Warning:
The lithium battery is not field replaceable. It must only be removed and replaced by authorized
personnel. Contact Technical Support for assistance if the battery requires replacement.
Before you begin
Ensure the area where you install and use the Extreme Networks Virtual Services Platform 4000
switch meets the following environmental requirements:
• Ambient temperature between 0° and 70° C
• Relative humidity between 0% and 95% noncondensing
• No nearby heat sources such as hot air vents or direct sunlight
• No nearby sources of severe electromagnetic noise
• No excessive dust
• Adequate power source within six feet; one 15-Amp circuit required for each power supply
• At least 2 inches (5.08 cm) on all sides of the switch unit for ventilation
• Adequate space at the front and rear of the switch for access to cables
If you are installing a single VSP 4000 switch on a table or shelf, ensure the surface can support at
least 15 to 20 pounds (7 to 9 kilograms).
Installing the VSP 4450GTX-HT-PWR+
Note:
Do not use the ERS to VSP conversion kit with this chassis. The kit is incompatible with the
VSP 4450GTX-HT-PWR+.
November 2017 Installation Job Aid for VSP 4450GTX-HT-PWR+ 3