Installation Guide
Table Of Contents
- Contents
- About this Document
- Product Overview
- Installing a Brocade MLX Router
- Installation precautions
- Installing 2x100GbE interface modules in Brocade MLX routers
- Installing a Brocade MLX-4 router
- Installing a Brocade MLX-8 router
- Installing a Brocade MLX-16 router
- Installing a Brocade MLX-32 router
- Installing a Brocade MLX-32 router
- Preparing the installation site
- Brocade MLX-32 router shipping carton contents
- Unpacking your Brocade MLX-32 router
- Installing a Brocade MLX-32 router in a rack
- Installing Brocade MLX-32 router modules
- Brocade MLX-32 cable management
- Accessing modules for service
- Installing power supplies in a Brocade MLX-32 router
- Connecting AC power
- Connecting DC power
- Removing Brocade MLX-32 router DC power supplies
- Final steps
- Attaching a management station
- Activating the power source
- Verifying proper operation
- Installing a NetIron XMR Router
- Installation precautions
- Installing 2x100GbE interface modules in NetIron XMR routers
- Installing a NetIron XMR 4000 router
- Installing a NetIron XMR 8000 router
- Installing a NetIron XMR 16000 router
- Installing a NetIron XMR 32000 router
- Preparing the installation site
- Unpacking a NetIron XMR 32000 router
- Installing a NetIron XMR 32000 router in a rack
- Installing NetIron XMR 32000 modules
- NetIron XMR 32000 cable management
- Accessing modules for service
- Installing NetIron XMR 32000 router power supplies
- Removing NetIron XMR 32000 router DC power supplies
- Final steps
- Attaching a management station
- Activating the power source
- Verifying proper operation
- Using Brocade Structured Cabling Components
- Cable cinch overview
- mRJ21 procedures
- RJ45 procedures
- Cable cinch with one group of RJ45 cables
- Cable cinch with two groups of RJ45 cables
- Cable cinch with three groups of RJ45 cables
- Cable cinch with four groups of RJ45 cables
- Cable cinch with five groups of RJ45 cables
- Cable cinch with six groups of RJ45 cables
- Cable cinch with seven groups of RJ45 cables
- Cable cinch with eight groups of RJ45 cables
- Connecting a Router to a Network Device
- Managing Routers and Modules
- Managing the device
- Enabling and disabling a DC Power Source
- Disabling and re-enabling power to interface modules
- Monitoring I2C failures on management modules
- Displaying device status and temperature readings
- Displaying the Syslog configuration and static and dynamic buffers
- MP Presence from LP Detection (Headless Router Operation)
- Rolling Reboot
- Line Module Configuration Deletion in Interactive Boot Mode
- Managing switch fabric modules
- Managing the cooling system
- Managing interface modules
- Monitoring Link Status
- Using alarms to collect and monitor device status
- Displaying MR2 management module memory usage
- Enabling and disabling management module CPU usage calculations
- Displaying management module CPU usage
- Removing MAC address entries
- Simplified Upgrade
- Managing the device
- Maintenance and Field Replacement
- Hardware Specifications
- Regulatory Statements
- Caution and Danger Notices
Brocade MLX Series and Brocade NetIron XMR Installation Guide 153
53-1004195-03
Installing a NetIron XMR 8000 router
FIGURE 107The NetIron XMR 8000 DC power supply
3. Use a #2 Phillips screwdriver to remove the power lugs, as shown in Figure 107.
4. Crimp the correct AWG power supply wire into the power lugs and reconnect the lugs to the power supply:
For a 1200 W power supply, crimp #8 AWG
For a 1800 W power supply, crimp #6 AWG
For the NEBS-compliant installation of a NetIron XMR 4000, 8000, and 16000 routers with AC and DC
system use a ground wire of at least 6 American Wire Gauge (AWG). The ground wire should have an
agency-approved crimped connector (provided with the router) attached to one end, with the other end
attached to building ground. The connector must be crimped with the proper tool, allowing it to be
connected to both ground screws on the enclosure. Before crimping the ground wire into the provided
ground lug, insure the bare copper wire has been cleaned and antioxidant is applied to the bare wire.
To ensure adequate bonding when attaching the ground lug, a minimum of 20 PSI of torque is required to
be applied to the mounting hardware used to attach the ground lug.
FIGURE 108Crimping the power supply wire in the lug
1 Screws holding transparent cover 2 Screws holding power lugs
DC OUT
ALM
DC IN
1
2