126 Extreme Networks Consolidated "e" and "i" Series Hardware Installation Guide
Installing and Connecting Summit Power Supplies
Figure 64: Redundant Power Cable with Key
Figure 65: Redundant Power Connection
8 Connect the other end of each EPS-160 power supply cable to the Extreme switch. This connector
end can only be inserted into the switch with the end marked TOP facing up.
9 Connect the supplied AC cable to the AC supply for each unit.
For countries other than the USA, you might require a different AC cable that is not supplied.
Contact your sales representative for the appropriate cable type and for information regarding the
voltage and current requirements of the power supply.
Adding a Second EPS-160 to the EPS-T
To install an individual EPS-160 in the EPS-T:
1 Remove the EPS-160 from the packing material.
2 Insert the EPS-160 into the front of the EPS-T.
3 Tighten the provided thumbscrews to secure the power supply to the tray.
4 Follows steps 7 through 9 on page 125.
Removing an EPS-160 from the EPS-T
To remove an EPS-160 from an EPS-T:
1 Disconnect the AC by removing the plug from the wall
2 Disconnect the AC power cord from the EPS-160.
ES4K027
ES4K021A
To A C
Slot for plug
Redundant
power cable
Keyed end of
redundant power cable