Setup Guide Instruction Manual

ETC Setup Guide
SmartPackā„¢ Portable
SmartPack Portable Setup Guide Page 4 of 6 Electronic Theatre Controls, Inc.
Installing the Power Supply Cable
Step 1: Slide the heat shrink tubing, enclosed with the SmartPack, over the power cord so that it
aligns with the back panel strain relief.
Step 2: Tighten the strain relief until snug. Do not over tighten.
Phase Cabling
Connect power supply cabling for standard installation. To modify factory wiring and change phase
cabling, reference the graphics below:.
WARNING:
Risk of electric shock! Damage or injury may occur if cable is incorrectly fitted.
When working on exposed load circuit wiring the load cables must be unplugged or
the unit disconnected from the power supply.
WARNING:
The power supply cable must be fitted and tested by a competent person.
The supply must be suitable protected by an external over-current device.
The SmartPack must not be exposed to dripping or splashing liquids and no objects
filled with liquid shall be placed on the SmartPack.
SmartLink data to CPU
(Factory wiring)
Strain Relief
Installation wiring
E
a
r
t
h
/
G
r
o
u
n
d
L
3
L
2
L
1
N
Earth NL1L2L3
Single Phase Configuration (Europe)
To Circuit Breakers
(factory wiring)
Important Note
Jumper wires must match specifications for
incoming line wire.
Earth NL1L2L3
Single Phase Configuration (US)
To Circuit Breakers
2C 1C
2B 1B
2A 1A
Three Phase Configuration
Earth NL1L2L3
To Circuit Breakers
(factory wiring)