2 The Retrofit 9
the panel a bit loose for the next step.
Step 9: Reinstall the tour guides (under the screw heads still in the rack) and fully tighten
the screws for each side. Be sure to install the guide under the plastic washers.
Note:
If your rack is an SP96 “Double Small” Frame without a convenience outlet in the
control input panel, it will be necessary to run the wiring for the new breaker and
convenience outlet to the A phase bar, neutral, and ground locations in the rack.
a: Run the white neutral convenience outlet wire to any existing slot on a
neutral bus.
b: Run the green ground
wire to any existing slot on
a ground bus.
c: Run the hot wire to the
open lug found at the top
of the top phase A bar. If
this lug does not exist,
one will need to be added
and is included in the kit.
Attach the lug using the
provided bolt, nut, and a
7/16” socket.
Run hot wire to this location
on top A phase bar