Installation manual
630167_5_Manual_Installation_US_R-emotion
Note:
THERE ARE A FEW THINGS TO CONSIDER BEFORE INSTALLATION
• Cavity Dimensions and Clearances
• MUST be installed a minimum of 4” above the floor or nearest horizontal surface.
• Coupling of flue to fireplace
• Gas pipe placement to the front left of the cavity.
• Coupling of gas lines to fireplace
• Fixing the fireplace to cavity
• Before installation, ensure that the local distribution conditions (identification of the type
of gas and pressure) and the adjustment of the appliance are compatible.
• A list of replacement parts is in Appendix D at the end of this Installation Manual
The sequence in which you choose to do these tasks will vary depending on your individual
scenario. Please read these instructions fully before proceeding with the installation.
Leave the installation of the fascia panels until the very end of the installation and
commissioning to avoid damage to the fascia panels.
Recommended Installation Process:
The following diagram illustrates the steps required to install your gas fireplace, and the trades
required at each stage.
Builder
1. Construct Frame (Section 1.0 to 6.0)
Gasfitter
4. Install Flue + Flue Restrictor if required (Section 12.0 to 13.0)
5. Test fireplace and verify flame pattern is acceptable
6. Cover-up fireplace using packaging (Section 18.0)
Gasfitter
2. Install Gas Pipe (Section 7.0 to 8.0)
3. Install Fireplace (Section 9.0 to 11.0)
Ensure that you leave a gap between the studwork and fire
chassis to accept the wall lining if applicable.
Builder
7. Dry wall / clad chimney breast
Gasfitter
8. Commission the Gas Fireplace (Section 19.0)