7.0 Clean Pilot and Main Burner Jets:
With the burner removed the burner jet is now accessible. Remove the jet and clean
it using an appropriate method, such as using a micro drill or compressed air.
8.0 Clean Thermocouple:
With the Pilot Cover removed you now have access to clean the thermocouple. Do
this by wiping it down with a rag or other appropriate cleaning tools in order to
remove any soot from the surface.
9.0 Paint Firebox [if required]:
If there are any scrapes or damage to the paint on the inside of the firebox you may
wish to touch up the paint. To do this, use a suitable high temperature matt black
paint. Do not put any paint on the burner, as there is a risk of blocking burner ports.
10.0 Inspect Flue System [if possible]:
If you have access to the flue system, inspect it for damage or potential blockages
(including the cowl). Ensure each flue component is twist-locked into the adjacent
components, and that there are no combustible objects or material within 25mm of
either side or below flue components or 50mm above any flue components, as
shown in the diagram below:
11.0 General Clean and Inspection:
A general clean of the fire should be undertaken by wiping down or dusting all
accessible areas and surfaces.