Installation Checklist
Go through the following checklist to ensure you have installed the appliance correctly
Correctly sized cavity to suit your fascia and ue conguration
Correct clearances to combustibles and mantles around the fascia
An electrical isolating switch to the appliance, accessible after nished installation
Correctly sized gas supply with a pressure test point, ensuring adequate supply with
all other gas appliances in the dwelling running
A weather-tight installed Horizontal or Vertical Powerue Terminal with clearance as
specied by AS/NZ5601.1
If chosen, reasonable access to the outside face of the Horizontal Powerue Wall Ter-
minal for maintenance purposes and ue attached to the rear of the Horizontal Powerue
Wall Terminal leading back to the appliance (and similar for Vertical Powerue Terminals)
The electrical cable from the Powerue Terminal attached correctly and run back to
the appliance cavity in an electrically safe manner
The appliance xed to the cavity base
The appliance plugged into a mains electricity supply
All gas joints and pressure points leak tested, and suitable leak detection solution and
drop tests completed on gas pipework
Fuel bed correctly installed
Glass correctly tted
Operated the re and veried that it lights reliably and safely
Appliance functions checked, including thermostat operation, Flame Eect and Fan
Boost
Data label marked up with correct gas type, and dated by installer if converted during
installation