D3 Installing the Horizontal Powerue option
The location of the Horizontal Powerue Wall Terminal must be installed in accordance
with AS/NZS 5601.1 and any other relevant building codes. Avoid installing the Horizontal
Powerue Wall Terminal in areas exposed to high winds and extreme weather, if possible.
D4 Installing in Accordance with Relevant Codes
Some of those minimum clearances for a fan assisted wall terminal are listed below;
please refer to AS/NZS 5601.1 Gas installation standard for full guidance on the design of
the ue system. Where possible allow a greater clearance.
A Below eaves, balconies and other projections 200mm
B From the ground, above a balcony or other surface 300mm
C From a return wall or external corner 300mm
D From a gas meter or regulator vent 1000mm
E From electricity meter or fuse box 500mm
F From a drain pipe or soil pipe 75mm
G Horizontally from any building structure or obstruction 500mm
H From any other ue terminal or combustion air intake 300mm
J Horizontally from any openable window, door, non-mechanical air
inlet, or any other opening into a building with the exception of sub
oor ventilation (or 1500mm in direction of discharge)
300mm
K From a mechanical air inlet or spa blower 1000mm
N Vertically below any openable window, door, non-mechanical air
inlet, or any other opening into a building with the exception of sub
oor ventilation
150mm
6.2