7. INSTALLATION
This section details the configuration, installation, and verification procedures to be performed when installing or adding
the Jessica PBX Gateway subsystem to the EDACS Multisite Radio Network. Installation of Jessica can be divided into three
parts: 1) configuration and installation of Jessica components, 2) configuration and installation of equipment at the IMC, and
3) configuration of equipment at the sites. Please refer to section 7.1.7 for software and hardware upgrades.
Installation at Jessica
Add/modify parameters in CONFIG.DAT to enable features.
Connect and program the System Manager.
Configure and run cables for the PI.
Install and configure the MD110.
Install the interconnect cables from the MD110 to the PI.
Set up LAN-related configuration files based on the questionnaire in Appendix A of LBI-39039.
Installation at IMC
Install and connect cables for the PIM Controller and Audio Boards.
Set up the CEC/IMC Manager.
Install the interconnect cabling from the IMC to the PI.
Installation at Sites
Configure the Site Controller personality.
Configure the GETC personality.
All PI and MD110 boards are static-sensitive. ESD handling procedures must be followed when replacing or installing
boards. Failure to do so may result in board failure or shortened board life.
The following additional documents are referenced in performing steps of the Jessica installation:
LBI-38703, EDACS VAX/VMS System Manager Installation, Setup and Troubleshooting
LBI-38938, CEC/IMC Installation, Set-Up and Troubleshooting
LBI-38939, CEC/IMC Customer-Specific System Documentation Overview
LBI-38984, EDACS VAX/VMS System Manager User’s Manual
LBI-39039, EDACS Jessica PBX Gateway MD110 Configuration Manual
LBI-39040, EDACS Jessica PBX Gateway PI User’s Manual
EN/LZB 103 866, Installation MD110/50
LZY 203 5001/30 Electronic Manual for ASB 50104 (MD110)
CAUTION