DESCRIPTION 9 ( 12 )
EIN/R/I Maude Andersson 1/1553-COH 109 334/1 Uen
ERA/RGG/THC 2002-05-31 B
Prepared (also subject responsible if other) No
Approved Checked Date Rev Reference
E
Figure 7 Grounding Connection Interface
All cabinets must be connected to the same grounding point inside the
equipment room.
Two grounding points are located on the cabinet top on the left and right side of
the ventilation net. See figure 7 for a detailed view. If only one of the grounding
points is used, choose the grounding point with the most suitable location. The
grounding point connectors are two M8 screws with M8 cable lugs. Grounding
can be made using either one or both of the grounding points.
1.5.2 Power Connection Interface
figure 8 shows the power connection interface for the RBS 3202.
Figure 8 Power Connection Interface
The power connection interface is located on the cabinet top in a black
protective box (shown in figure 8). The recommended power cables dimension
is 70 mm² and the power connectors are two M8 screws with washers and
M8 cable lugs.
1.5.3 Antenna Connection Interfaces
figure 9 shows the antenna connection interfaces for the RBS 3202.
Figure 9 Antenna Connection Interfaces
The antenna connection interfaces are located on the cabinet top; three
antenna feeder connectors on each side. The connectors are 7/16 IEC-169–4
female connectors.
The connectors are labeled position H1 to position H3 on the left-hand top of
the cabinet and position J1 to position J3 and on the right-hand top of the
cabinet. See figure 9 for a detailed view of the connectors.
The antenna cables must be connected as follows:
Sector 1A to position J1
Sector 1B to position H1
Sector 2A to position J2
Sector 2B to position H2